Public Information Services Timelines

Public Information Services Development Guidelines

 

Editorial Services (if needed):

Write New Copy - Allow 4 weeks

Edit Copy - Allow 2 weeks

 

Design:

New Job - Allow 4 weeks

Redesign - Allow 3 weeks

Update - Allow 2 weeks     

 

Proofing:

New or Updated Materials - Allow 1 week

 

Videography:

Script Review - Allow 1 week

Script Writing - Allow 4 weeks

 

Printing (External):

Four-color - Allow 2-4 weeks

Two-color - Allow 1-2 weeks

 

Please note!

Each service is provided by a separate person/area; please add times and count back from your desired delivery date to arrive at a reasonable time to submit your request. Failure to respond to questions, return proofs promptly, or submit a requisition and provide a PO number will result in project delays. All requests will be evaluated in terms of UF mission priority and appropriateness, and deadlines and delivery times may be adjusted to reflect that.

 

One week equals five working days.